The work consists of construction of three storyes RCC framed staff quarter building having plinth area 196.28 square meters. Construction of one storey RCC frmed guard house having plinth area 47.30 square meters. Construction of one storey ware- house with corrugated galvanized iron sheet roofing having plinth area 119.34 square meters and construction of boundary wall (Total length-553.45RM)with stone masonry, brick masonry and chain link fence.

The Employer is:

Nepal Electricity Authority, Government of Nepal Undertaking, Transmission Directorate, Grid Development Department, Syaule 132 KV Substation Project

Project Hightlight

Construction of Staff Quarter and Other Miscellaneous works at Syaule 132 KV Substation
  • Building
  • NCB-SSP 072/073-1
  • NPR 50,995,971.52
  • Prime